Stream service is down - Unable to move Queue Processor to Running State

Hi,

Queue Processor Management Page in Admin studio, always shows the below message

"Stream service is down. The values displayed on this page may be inaccurate"

And i'm unable to move any available Queue Processor from Failed state to Running State.

Thanks in Advance,
Saiful Haq

Correct Answer
April 25, 2019 - 6:34am

Can you click on action, decommission and add it again to see what is status?

Do share logs for this duration of test.

Comments

Keep up to date on this post and subscribe to comments

April 24, 2019 - 6:45am

Can you please share relevant logs ?

What is state of Stream nodes under decision-infra -stream node landing page?

April 25, 2019 - 6:27am
Response to ARVINDMALAV

Stream node is in STOPPED state.

April 25, 2019 - 6:34am

Can you click on action, decommission and add it again to see what is status?

Do share logs for this duration of test.

April 25, 2019 - 7:16am
Response to ARVINDMALAV

It has turned to Status NORMAL. And the Queue Processor just started processing the queue items.

Thank You!