Assignment Missing

I am using PRPC5.1 sp1
many times i found assignment missing.

I have some work objects in the middle of the flow. whose assignments arer missing. I want to move them to down.
Please suggest me some way. I dont want to take the work objects to starting of the flow by creating a new flow again.

please advise.

**Moderation Team has archived post**

This post has been archived for educational purposes. Contents and links will no longer be updated. If you have the same/similar question, please write a new post.

Comments

Keep up to date on this post and subscribe to comments

December 15, 2008 - 9:27am

Is the Clipboard ->Start Flow option helpful in your case? You can start specific flow where the assignment is missing.

December 18, 2008 - 10:01am

it still creating the assignment and taking it to starting of the flow.
I want the assignment to be at the same postion.

December 30, 2008 - 11:47am

Have you traced the movement of the work object flowing through the flow to your assignment where it appears to be not saving/Comiting.

Check for any errors on the tracer.
I have come acorss this problem many times, it might be that the case isnt saving/comit correctly.

Hope this might give you a lead.

Pega
January 2, 2009 - 3:13pm

Generally this sort of problem occurs when there is a commit somewhere in flow processing. The sequence goes something like this:

- user clicks submit on flow action
- PRPC does a deferred delete of the assignment
- an activity called from the flow issues a commit; the assignment is deleted for real
- later in the flow an error occurs
- PRPC does a rollback but it is too late to recover the deleted assignment.

There are many variations on this scenario, but they usually boil down to activities performing database i/o and then later an error occurring.

March 30, 2016 - 6:52am

run FixProblemAssignment activity by passing pzinskey of case  from work table